- Χώρα
- Greece
- Τοποθεσία
- SEMBO IKONIO
- Υπηρεσία
- Floor Repairs & Services
- Τύπος δαπέδου
- Floor Repair
- Έτος
- 2026
The PCDC AE cold storage facility, located within the Piraeus Container Terminal at Perama, faced a critical operational challenge. The concrete floor transition at the freezer chamber entrance had suffered severe structural degradation and cracking. These high-traffic thresholds are particularly vulnerable due to extreme thermal shock—the result of the vast temperature differential between the ambient exterior and the -20°C interior.
The resulting cracks and surface spalling created hazardous conditions for forklift and pallet jack traffic, risking both equipment damage and personnel safety. Crucially, the client required a structural repair that could be executed without decommissioning the freezer chamber. This meant the solution had to be applied at -20°C and return the area to full operational capacity within a strict 48-hour window to prevent logistics disruptions.